North Apron – Civil Contract 1

In advance of DAA plc’s planned Apron Phase 5H development proceeding, existing aircraft stands have to be relocated to facilitate this project. This North Apron Civil Contract 1 entailed the upgrade of existing pavements adjacent to hangers 5 and 6 at Dublin Airport to provide additional aircraft stand parking.

This Project was delivered in two main works phases and included the following;

  • • Provision of drainage infrastructure including F900 loading channels
  • • Provision of new rigid and flexible pavements (16,000m2)
  • • Provision of all electrical infrastructure for ground lighting, High Mast Lighting etc.
  • • Diversion and replacement of existing critical utility infrastructure
  • • Traffic Management for all third party airport related operational activities through the works
  • LocationDublin Airport
  • ClientDAA plc
  • Client's RepresentativeRamboll
  • Contract Completed2020